Booking January Installs: How to Sequence Window Treatment Orders Through the Holidays
    Trade Resources

    Booking January Installs: How to Sequence Window Treatment Orders Through the Holidays

    Roseworks Fabrication··4 min read

    Short answer: If a project is not already in production by mid-November, plan for a January install and use the holiday weeks to finish everything that slows a job down. Lock measurements, get written client approval on fabric and style, confirm fabric availability and place holds, and release the order with deposits before the December slowdown. Orders that arrive complete in late November start cleanly in the first weeks of January.

    Thanksgiving is next week, and every designer has the same conversation with at least one client: can it be up for the holidays? For orders that are not already cut, the honest answer is usually no, and the better answer is a plan. This post covers how to use late November and December so a January install happens on the date you promise. For the earlier part of the season, see our fall production calendar, and for managing the client side, our post on timeline expectations.

    Why do orders placed in late November usually install in January?

    Production queues are at their fullest in November, fabric shipping slows around the holidays, and installers' calendars fill with jobs that were ordered in early fall. Add Thanksgiving and the December holidays, when clients travel and homes are full of guests, and late-November orders naturally fall into January. That is not a delay. It is the calendar.

    The jobs that slip past January are the ones that reach the workroom incomplete. Missing measurements, an unapproved fabric, or a backordered lining can each add weeks.

    What should be finished before you release an order?

    Five things decide whether an order moves straight into production: final measurements, written client approval of fabric and style, confirmed fabric availability, complete specifications, and the deposit. If any one of them is missing, the order waits. In December, waiting a week can mean waiting until the next production window.

    ItemWhy it matters in DecemberDone when
    Final measurementsRe-measures are hard to schedule over the holidaysEvery opening measured and photographed
    Client approval in writingClients travel and replies slow downSigned off on fabric, style, and lining
    Fabric availabilityMills and distributors slow down at year-endStock confirmed and a hold placed
    Complete specificationsQuestions stall the cutting tableMount, fullness, hardware, and lining listed
    Deposit receivedOrders do not start without itPayment confirmed with the workroom

    How do you sequence the next six weeks?

    Work backward from the install date you want in January. Lock the client decisions first, because those take the longest over the holidays. Then confirm fabric, then release the order, then schedule install. Keep the install date flexible by a week until fabric is confirmed in hand.

    A practical sequence for designers:

    1. Before Thanksgiving: finish measuring every room on the job, including the hard ones like bays and stair windows.
    2. Thanksgiving week: send the client a single approval packet with fabric, style, lining, and hardware for every room.
    3. First week of December: confirm fabric stock, place holds, and order any hardware with its own lead time.
    4. Second week of December: release the complete order and deposit to the workroom.
    5. Late December: confirm the install window with the client and the installer.
    6. January: install, then photograph the finished rooms for your portfolio.

    How do fabric holds and backorders affect a January install?

    Fabric is the item most likely to move your date. A fabric that shows in stock today can be sold through by the time the order is placed. Ask the source to hold the yardage once the client approves it, and confirm it again on the day you release the order. If a fabric is backordered, decide immediately whether to wait or substitute, and get the client's sign-off on the alternate in writing.

    Linings and interlinings run short at year-end too, especially for winter projects. Our post on interlined drapery for Colorado winters explains which lining choices change yardage and lead time.

    What can the client enjoy before the install?

    Clients rarely mind a January date when they know exactly what is coming. Send them a sample board, a fabric cutting, and a rendering or inspiration photo before the holidays so the project feels started. If privacy is the real concern in a guest room, a simple temporary shade can bridge the gap until custom treatments arrive.

    How should commercial and multifamily jobs be handled?

    Commercial jobs carry extra paperwork, such as flame-retardant certificates, and often have to fit a property's move-in or event calendar. Start those orders even earlier and confirm every certificate before release. Our NFPA 701 guide for commercial drapery lists what to gather. For odd-shaped openings that tend to hold up approvals, see our post on bay and corner window fabrication.

    Frequently asked questions

    Can anything still be installed before the holidays?

    Orders already in production may still make it. Ask for the current schedule on your specific order. New orders placed now should plan for January.

    What is the most common reason a January install slips?

    An incomplete order. Missing measurements, open client decisions, and unconfirmed fabric account for most delays.

    Should I place the order before the client approves everything?

    No. Release complete orders. A partial order that waits on a decision holds a production slot without moving.

    How much flexibility should I build into a January date?

    Keep the install date flexible by about a week until fabric is in hand at the workroom. Then lock it with the client.

    Can I combine several rooms into one January install?

    Yes, and it is often easier for the client. Release the rooms together so they move through production as one job.

    How do I check the current lead time?

    Ask the workroom when you request the quote. Lead times move through the season, so confirm at the time of order rather than relying on last month's number.

    Plan your January installs with Roseworks

    Roseworks fabricates custom drapery, Roman shades, and soft goods for the design trade from our Westminster workroom. Send your next project through our trade program or contact the studio, and we will help you map a realistic January install date.

    lead timesJanuary installholiday scheduleproject managementtradeDenver workroom